PROJECT 5006: WESTIN HOTEL - DAILY MANPOWER

DATE: 02-May-2026
No. Position Shafa Local Zam Zam (Civil) ZBE (Electrical) UEC (Electrical) Extra Tech (Mech) Lucky General Trading Ararisa Tegenu (Surface Cleaning Contractor) EGB contractor PLC NERGEC Electro Mechanical and Importer company M/Y TTYL Fire Fighting Subcon Abham Enterprises Bambu construction Total
Direct Manpower
1 Civil Gang / Team Leader
2 Mason 2 2 1 1 6
3 Gypsum Plaster Mason
4 Carpenter 1 2 2 5
5 AC Ductman 1 1
6 Electrician 3 3 2 8
7 Plumber 1 2 3
8 Pipe Fitter 2 1 2 5
9 Fabricator for Safety edge protection
10 Civil Helper 1 1 1 1 1 1 1 1 1 2 1 12
11 Labourer 1 2 1 1 1 1 3 2 1 4 3 1 21
12 Chiseler
13 Applicator
14 Cleaner 1 2 2 3 1 9
Indirect Manpower
1 Project Manager 1 1
2 Civil Construction Manager 1 1
3 Planning Manager
4 QA/QC Manager
5 MEP Construction Manager
6 Safey Manager
7 MEP Coordinator 1 1
8 Planning Engineer 1 1
9 Sr Civil Site Engineer
10 QA/QC Engineer
11 Sr HVAC Engineer
12 Sr Electrical Engineer 1 1 2
13 Mechanical Engineer 1 1
14 Quantity Surveyor 1 1
15 Sr. Project Engineer 1 1
16 Architect
17 Civil Site Engineer 1 1 2
18 Gypsum Engineer
19 Fire Fighting Engineer 1 1
20 Sr. CAD Draftman
21 Finance (Accounts) 1 1
22 Surveyor
23 Sr. Civil Foreman 1 1 2
24 Plumbing Supervisor 1 1
25 General Foreman 1 1
26 Foreman 1 1 2
27 Charge Hand - Electrical 1 1 2
28 Time keeper 1 1 2
29 Store keeper 1 1
30 Generator Operator
31 Service Lift Operator / Hoist Operator
32 Data Collector 1 1
33 Lift Operator 1 1
34 Nurse
35 Office Cleanrer 1 1
36 Hse Manager 1 1
Total Personnel 7 7 7 7 7 7 7 7 7 7 7 7 7 7 98